40 MW storage in Middlesex, VA · In queue since April 2019 · Proposed COD March 2026
40 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 11m
Schedule
1 months past proposed COD
Construction75%
Queue EntryApr 3, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
VA
County
Middlesex
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Harmony Village 230 kV