Maryland Offshore Wind Energy Project (MOWEP)
BetaSuspendedOffshore WindPJMLBNL + Live
7.3 MW generation in Sussex, DE · In queue since April 2019 · Proposed COD December 2027
7.3 MW
Capacity
1
Components
Offshore Wind
6y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 8m
Suspended75%
Queue EntryApr 1, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 36–60 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
DE
County
Sussex
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Indian River 230 kV I
Data Source
LBNL + Live
No news available for this project.