Charles County Solar I
BetaSuspendedSolarPJMLBNL + Live
20 MW generation in Charles, MD · In queue since April 2019 · Proposed COD September 2028
20 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 5m
Suspended50%
Queue EntryApr 1, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
MD
County
Charles
Region
PJM
Developer
—
Utility
SMECO
Entity
PJM
Point of Interconnection
Grayton-Ripley 69 kV
Data Source
LBNL + Live