Wythe County Solar Project
52.2 MW storage in Wythe, VA · In queue since March 2019 · Proposed COD June 2027
52.2 MW
Capacity
1
Components
Battery
7 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-15
State
VA
County
Wythe
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jacksons Ferry 138 kV
Data Source
LBNL + Live
Dominion Energy Virginia signs 75-MW solar PPA with Savion
The Wythe County Solar Project is expected to begin construction in mid-2021, with commercial operation targeted by the end of 2022.
Dominion Energy Virginia signs 75-MW solar PPA with Savion
The Wythe County Solar Project is expected to begin construction in mid-2021, with commercial operation targeted by the end of 2022.
Dominion Energy Virginia signs 75-MW solar PPA with Savion
The Wythe County Solar Project is expected to begin construction in mid-2021, with commercial operation targeted by the end of 2022.
Dominion Energy Virginia signs 75-MW solar PPA with Savion
The Wythe County Solar Project is expected to begin construction in mid-2021, with commercial operation targeted by the end of 2022.
Last updated 2026-03-26