Elkhart County Solar Project
100 MW generation in Elkhart, IN · In queue since March 2019 · Proposed COD May 2026
100 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-01
State
IN
County
Elkhart
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Twin Branch-Guardian 138 kV
Data Source
LBNL + Live
Commissioners Deny Zoning for Solar Energy
Elkhart County, Indiana (October 11, 2021) – Elkhart County Commissioners today voted to deny a rezoning request for the Elkhart County Solar Project which...
Elkhart County Solar Project comes to its final votes
Kansas City-based energy firm Savion wants to build a solar farm on 850 acres of land south of Millersburg. The facility would generate up to 150 megawatts of...
Elkhart County Solar Project comes to its final votes
Kansas City-based energy firm Savion wants to build a solar farm on 850 acres of land south of Millersburg. The facility would generate up to 150 megawatts of...
Elkhart County Solar Project comes to its final votes
Kansas City-based energy firm Savion wants to build a solar farm on 850 acres of land south of Millersburg. The facility would generate up to 150 megawatts of...
Last updated 2026-03-14