Madison Solar 1
BetaActiveSolarPJMLBNL
100 MW generation in Madison, KY · In queue since March 2019 · Proposed COD May 2021
100 MW
Capacity
1
Components
Solar
7 years
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 2m
Schedule
59 months past proposed COD
Impact Study25%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-05-31
Project Details
State
KY
County
Madison
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Three Forks-Dale 138 kV
Data Source
LBNL