BetaActiveSolarPJMLBNL + Live
78 MW generation in Champaign, OH · In queue since March 2019 · Proposed COD September 2029
78 MW
Capacity
1
Components
Solar
7 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10y 6m
Facilities Study50%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-09-30
Project Details
State
OH
County
Champaign
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Givens-Mechanicsburg 138 kV
Data Source
LBNL + Live
No news available for this project.