Erie East Energy
BetaSuspendedBatteryPJMLBNL + Live
160 MW storage in Erie, PA · In queue since March 2019 · Proposed COD June 2026
160 MW
Capacity
1
Components
Battery
7 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 3m
Suspended75%
Queue EntryMar 22, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
PA
County
Erie
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Erie East 230 kV
Data Source
LBNL + Live