Nottingham Solar — Project Summary

Queue ID
PJM-AE2-290
Capacity
100 MW
Technology
Solar
Status
active
Location
Harrison, OH
Region
PJM
Developer
IA Status
IA Executed

Nottingham Solar

BetaActiveSolarPJMLBNL + Live

100 MW generation in Harrison, OH · In queue since March 2019 · Proposed COD December 2023

100 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 9m

Schedule

28 months past proposed COD

Construction75%
Queue EntryMar 29, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-12-15

Project Details

State

OH

County

Harrison

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Nottingham 138 kV

Data Source

LBNL + Live