Nottingham Solar
100 MW generation in Harrison, OH · In queue since March 2019 · Proposed COD December 2023
100 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 9m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-12-15
State
OH
County
Harrison
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Nottingham 138 kV
Data Source
LBNL + Live
Two solar projects in Ohio approved
The Ohio Power Siting Board approved applications filed by Wild Grains Solar, LLC and Nottingham Solar LLC for solar-powered electric...
Hearing set in Harrison Co. for solar farm
The Ohio Power Siting Board will hold a hearing for Nottingham Solar LLC's proposal to construct a 100-megawatt solar-powered electric...
Last updated 2026-03-26