BetaActiveWindPJMLBNL + Live
80 MW generation in Allegany, MD · In queue since March 2019 · Proposed COD December 2021
80 MW
Capacity
1
Components
Wind
7 years
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 9m
Schedule
52 months past proposed COD
Facilities Study50%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
MD
County
Allegany
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Frostburg 138 kV
Data Source
LBNL + Live