Panther Grove Wind
BetaActiveWindPJMLBNL + Live
50 MW generation in Woodford, IL · In queue since March 2019 · Proposed COD February 2027
50 MW
Capacity
1
Components
Wind
7 years
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 11m
Construction75%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-02-01
Project Details
State
IL
County
Woodford
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Powerton-Nevada 345 kV
Data Source
LBNL + Live
No news available for this project.