Trade Post Energy Storage — Project Summary

Queue ID
PJM-AE2-276
Capacity
50 MW
Technology
Battery
Status
active
Location
Sullivan, IN
Region
PJM
Developer
IA Status
IA Executed

Trade Post Energy Storage

BetaActiveBatteryPJMLBNL + Live

50 MW storage in Sullivan, IN · In queue since March 2019 · Proposed COD December 2028

50 MW

Capacity

1

Components

Battery

7 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 9m

Construction75%
Queue EntryMar 28, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

IN

County

Sullivan

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Sullivan 345kV

Data Source

LBNL + Live

No news available for this project.