Woodsdale Renewable Energy Center
BetaActiveSolarPJMLBNL + Live
49 MW generation in Butler, OH · In queue since March 2019 · Proposed COD June 2026
49 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 3m
Construction75%
Queue EntryMar 29, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
OH
County
Butler
Region
PJM
Developer
—
Utility
DEOK
Entity
PJM
Point of Interconnection
Woodsdale 345 kV
Data Source
LBNL + Live
No news available for this project.