— Project Summary

Queue ID
PJM-AE2-261
Capacity
299 MW
Technology
Solar
Status
active
Location
Christian, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

299 MW generation in Christian, IL · In queue since March 2019 · Proposed COD June 2022

299 MW

Capacity

1

Components

Solar

7 years

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

46 months past proposed COD

Impact Study25%
Queue EntryMar 28, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-06-01

Project Details

State

IL

County

Christian

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Kincaid-Pana 345 kV

Data Source

LBNL

No news available for this project.