BetaActiveSolarPJMLBNL
299 MW generation in Christian, IL · In queue since March 2019 · Proposed COD June 2022
299 MW
Capacity
1
Components
Solar
7 years
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 3m
Schedule
46 months past proposed COD
Impact Study25%
Queue EntryMar 28, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-01
Project Details
State
IL
County
Christian
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Kincaid-Pana 345 kV
Data Source
LBNL
No news available for this project.