Blue Rock Solar — Project Summary

Queue ID
PJM-AE2-259
Capacity
100 MW
Technology
Solar
Status
active
Location
Buckingham, VA
Region
PJM
Developer
IA Status
IA Executed

Blue Rock Solar

BetaActiveSolarPJMLBNL + Live

100 MW generation in Buckingham, VA · In queue since March 2019 · Proposed COD December 2026

100 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 9m

Construction75%
Queue EntryMar 28, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

VA

County

Buckingham

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Curdsville-Willis Mtn 115 kV

Data Source

LBNL + Live