CE-FILMORE
BetaSuspendedSolarPJMLBNL + Live
16 MW generation in Centre, PA · In queue since March 2019 · Proposed COD December 2027
16 MW
Capacity
1
Components
Solar
7 years
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 9m
Suspended25%
Queue EntryMar 25, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
PA
County
Centre
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Fillmore-Thompson Farm 46 kV
Data Source
LBNL + Live
No news available for this project.