Dover Solar Facility — Project Summary

Queue ID
PJM-AE2-236
Capacity
55 MW
Technology
Solar
Status
suspended
Location
Whitley, IN
Region
PJM
Developer
IA Status
IA Executed

Dover Solar Facility

BetaSuspendedSolarPJMLBNL + Live

55 MW generation in Whitley, IN · In queue since March 2019 · Proposed COD July 2026

55 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 4m

Suspended75%
Queue EntryMar 22, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-07-29

Project Details

State

IN

County

Whitley

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Columbia-Northeast 138 kV

Data Source

LBNL + Live