Maple Solar
35 MW generation in Huntington, IN · In queue since March 2019 · Proposed COD December 2028
35 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-31
State
IN
County
Huntington
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Liberty Center-Buckeye Tap 69 kV
Data Source
LBNL + Live
Solar plan near Zeeland creates tension among farmers, residents
Hudsonville — Global energy company RWE held a public hearing March 17 to hear concerns from the public about a 1,900-acre proposed solar...
1,900-acre Ottawa County solar farm faces pushback at public meeting
A large-scale commercial solar farm proposed for Ottawa County is attempting to gain the favor of residents after months of public outcry.
Zeeland and Jamestown neighbors upset over farmland being used in future solar project
HUDSONVILLE, Mich. — One moment stood out during the public meeting over the Silver Maple Solar Project at Evergreen Ministries on Tuesday...
Zeeland and Jamestown neighbors upset over farmland being used in future solar project
HUDSONVILLE, Mich. — One moment stood out during the public meeting over the Silver Maple Solar Project at Evergreen Ministries on Tuesday...
Last updated 2026-03-26