Riverstart Solar Park II — Project Summary

Queue ID
PJM-AE2-220
Capacity
125 MW
Technology
Solar
Status
active
Location
Randolph, IN
Region
PJM
Developer
IA Status
IA Executed

Riverstart Solar Park II

BetaActiveSolarPJMLBNL + Live

125 MW generation in Randolph, IN · In queue since March 2019 · Proposed COD November 2027

125 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 8m

Construction75%
Queue EntryMar 21, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-11-15

Project Details

State

IN

County

Randolph

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Losantville 345 kV

Data Source

LBNL + Live

No news available for this project.