Riverstart Solar Park V
BetaSuspendedSolarPJMLBNL + Live
100 MW generation in Randolph, IN · In queue since March 2019 · Proposed COD May 2026
100 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 2m
Suspended75%
Queue EntryMar 21, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-31
Project Details
State
IN
County
Randolph
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Bluff Point-Randolph 138 kV
Data Source
LBNL + Live