Pleasant Prairie Solar Energy Center
200 MW generation in Franklin, OH · In queue since March 2019 · Proposed COD March 2027
200 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-30
State
OH
County
Franklin
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Cole 345 kV
Data Source
LBNL + Live
Meta purchases 791MW of renewable power from Invenergy across four projects in US
The tech giant signed four renewable energy agreements across four projects in Ohio (x2), Arizona, and Texas, for a combined capacity of 791MW.
Meta, Invenergy Expand Partnership with 791 MW Clean Energy Deal
After 791 MW of solar and wind capacity, the total contracted renewable energy between Meta and Invenergy have now increased to 1800 MW.
Meta purchases 791MW of renewable power from Invenergy across four projects in US
The tech giant signed four renewable energy agreements across four projects in Ohio (x2), Arizona, and Texas, for a combined capacity of 791MW.
Meta purchases 791MW of renewable power from Invenergy across four projects in US
The tech giant signed four renewable energy agreements across four projects in Ohio (x2), Arizona, and Texas, for a combined capacity of 791MW.
Last updated 2026-03-26