Dover Solar
55 MW generation in York, PA · In queue since March 2019 · Proposed COD September 2027
55 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-07
State
PA
County
York
Region
PJM
Developer
—
Utility
ME
Entity
PJM
Point of Interconnection
Jackson-Three Mile Island 230 kV
Data Source
LBNL + Live
Second solar farm proposed for Dover Township: Residents ask why here?
The solar farm, proposed by solar Renewable Energy, would sit on 27 acres of land at 5370 Harmony Grove Road. It would contain 10,...
Second solar farm proposed for Dover Township: Residents ask why here?
The solar farm, proposed by solar Renewable Energy, would sit on 27 acres of land at 5370 Harmony Grove Road. It would contain 10,...
Dover Solar Farm project approved after 7 hearings on the matter
The Dover Township Zoning Board has approved a request for a special use exemption for a 600-acre-plus solar farm that would spread east of...
Residents throw shade at Dover Solar Project, but farms are cropping up across York County
The controversial Dover Solar Project faced a third round of public comment at the township's zoning board Wednesday.
Last updated 2026-03-26