Dover Solar — Project Summary

Queue ID
PJM-AE2-211
Capacity
55 MW
Technology
Solar
Status
active
Location
York, PA
Region
PJM
Developer
IA Status
IA Executed

Dover Solar

BetaActiveSolarPJMLBNL + Live

55 MW generation in York, PA · In queue since March 2019 · Proposed COD September 2027

55 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 6m

Construction75%
Queue EntryMar 20, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-09-07

Project Details

State

PA

County

York

Region

PJM

Developer

Utility

ME

Entity

PJM

Point of Interconnection

Jackson-Three Mile Island 230 kV

Data Source

LBNL + Live