Swiftwater Solar — Project Summary

Queue ID
PJM-AE2-175
Capacity
80 MW
Technology
Solar
Status
active
Location
Monroe, PA
Region
PJM
Developer
IA Status
IA Executed

Swiftwater Solar

BetaActiveSolarPJMLBNL + Live

80 MW generation in Monroe, PA · In queue since March 2019 · Proposed COD December 2025

80 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6y 9m

Schedule

3 months past proposed COD

Construction75%
Queue EntryMar 19, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

PA

County

Monroe

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Jackson-Long Pond 69 kV

Data Source

LBNL + Live