Swiftwater Solar
80 MW generation in Monroe, PA · In queue since March 2019 · Proposed COD December 2025
80 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
6y 9m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-31
State
PA
County
Monroe
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Jackson-Long Pond 69 kV
Data Source
LBNL + Live
Wayne County solar farms: Permit pending near Lake Ariel, hearing set in Cherry Ridge Twp.
An applicant is seeking a state permit for a Salem Township solar farm project, and an April hearing is set for a Cherry Ridge Township...
Proposed Poconos solar field that would be Pa.'s largest gets permit from state
SWIFTWATER, Pa. – A proposal to build Pennsylvania's largest solar field on a mountain slope has gotten one of the final two permits...
New solar field project in Monroe County nears approval
During a Monday night meeting, Pocono Township officials granted Apex Clean Energy conditional approval to build a 475-acre solar field.
Environmental advocates support solar, but worry Swiftwater project will harm creek
An 80-megawatt solar field in Pocono Township will be up for conditional approval on Monday, a prospect that has environmental advocates concerned about the...
Last updated 2026-03-26