— Project Summary

Queue ID
PJM-AE2-173
Capacity
50 MW
Technology
Battery
Status
active
Location
Mclean, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveBatteryPJMLBNL

50 MW storage in Mclean, IL · In queue since March 2019 · Proposed COD December 2022

50 MW

Capacity

1

Components

Battery

7 years

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 9m

Schedule

39 months past proposed COD

Impact Study25%
Queue EntryMar 18, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

IL

County

Mclean

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

McLean 345 kV

Data Source

LBNL

No news available for this project.