Golden Aster Solar Energy Center — Project Summary

Queue ID
PJM-AE2-172
Capacity
40 MW
Technology
Battery
Status
suspended
Location
Grant, IN
Region
PJM
Developer
IA Status
IA Executed

Golden Aster Solar Energy Center

BetaSuspendedBatteryPJMLBNL + Live

40 MW storage in Grant, IN · In queue since March 2019 · Proposed COD May 2026

40 MW

Capacity

1

Components

Battery

7 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 2m

Suspended75%
Queue EntryMar 16, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-05-31

Project Details

State

IN

County

Grant

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Mississinewa-Gaston 138 kV

Data Source

LBNL + Live