BetaActiveHydroPJMLBNL + Live
51 MW generation in Fayette, WV · In queue since March 2019 · Proposed COD September 2028
51 MW
Capacity
1
Components
Hydro
7 years
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 6m
Facilities Study50%
Queue EntryMar 15, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-09-30
Project Details
State
WV
County
Fayette
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Kanawha River 138 kV
Data Source
LBNL + Live