BetaActiveBatteryPJMLBNL
100 MW storage in City Of Chesapeake, VA · In queue since March 2019 · Proposed COD December 2021
100 MW
Capacity
1
Components
Battery
7 years
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 9m
Schedule
53 months past proposed COD
Impact Study25%
Queue EntryMar 15, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-01
Project Details
State
VA
County
City Of Chesapeake
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Yadkin 115 kV
Data Source
LBNL
No news available for this project.