Appalachian Cottontail Solar — Project Summary

Queue ID
PJM-AE2-136
Capacity
114 MW
Technology
Solar
Status
active
Location
Fairfield, OH
Region
PJM
Developer
IA Status
IA Executed

Appalachian Cottontail Solar

BetaActiveSolarPJMLBNL + Live

114 MW generation in Fairfield, OH · In queue since March 2019 · Proposed COD December 2028

114 MW

Capacity

1

Components

Solar

7 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 9m

Construction75%
Queue EntryMar 6, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OH

County

Fairfield

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Muskingum River-W. Millersport 345 kV

Data Source

LBNL + Live