HU-Logging
BetaSuspendedSolarPJMLBNL + Live
20 MW generation in Huntingdon, PA · In queue since February 2019 · Proposed COD August 2024
20 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
5y 6m
Suspended75%
Queue EntryFeb 28, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-08-31
Project Details
State
PA
County
Huntingdon
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
ABW Tap-Williamsburg 46 kV
Data Source
LBNL + Live
No news available for this project.