Potter Solar
BetaActiveSolarPJMLBNL + Live
35 MW generation in Potter, PA · In queue since February 2019 · Proposed COD July 2026
35 MW
Capacity
1
Components
Solar
7y 1m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 5m
Impact Study25%
Queue EntryFeb 20, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-07-31
Project Details
State
PA
County
Potter
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Potter 46 kV
Data Source
LBNL + Live
No news available for this project.