Potter Solar — Project Summary

Queue ID
PJM-AE2-074
Capacity
35 MW
Technology
Solar
Status
active
Location
Potter, PA
Region
PJM
Developer
IA Status
System Impact Study

Potter Solar

BetaActiveSolarPJMLBNL + Live

35 MW generation in Potter, PA · In queue since February 2019 · Proposed COD July 2026

35 MW

Capacity

1

Components

Solar

7y 1m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 5m

Impact Study25%
Queue EntryFeb 20, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-07-31

Project Details

State

PA

County

Potter

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

Potter 46 kV

Data Source

LBNL + Live

No news available for this project.