Henry County Solar Facility — Project Summary

Queue ID
PJM-AE2-047
Capacity
50 MW
Technology
Solar
Status
active
Location
Henry, VA
Region
PJM
Developer
IA Status
IA Executed

Henry County Solar Facility

BetaActiveSolarPJMLBNL + Live

50 MW generation in Henry, VA · In queue since January 2019 · Proposed COD August 2027

50 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 7m

Construction75%
Queue EntryJan 31, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-08-31

Project Details

State

VA

County

Henry

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Ridgeway-Solite 69 kV

Data Source

LBNL + Live