Bottlebrush Solar — Project Summary

Queue ID
PJM-AE2-045
Capacity
200 MW
Technology
Solar
Status
active
Location
Lake, IN
Region
PJM
Developer
IA Status
IA Executed

Bottlebrush Solar

BetaActiveSolarPJMLBNL + Live

200 MW generation in Lake, IN · In queue since January 2019 · Proposed COD March 2028

200 MW

Capacity

1

Components

Solar

7y 2m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 2m

Construction75%
Queue EntryJan 29, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-03-31

Project Details

State

IN

County

Lake

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Olive-Reynolds 345 kV

Data Source

LBNL + Live