Chester Solar
BetaActiveSolarPJMLBNL + Live
120 MW generation in Chesterfield, VA · In queue since December 2018 · Proposed COD October 2027
120 MW
Capacity
1
Components
Solar
7y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 10m
Construction75%
Queue EntryDec 20, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-10-29
Project Details
State
VA
County
Chesterfield
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Harrowgate-Locks 115kV
Data Source
LBNL + Live
No news available for this project.