New Road Storage — Project Summary

Queue ID
PJM-AE2-019
Capacity
120 MW
Technology
Battery
Status
active
Location
Loudoun, VA
Region
PJM
Developer
IA Status
IA Executed

New Road Storage

BetaActiveBatteryPJMLBNL + Live

120 MW storage in Loudoun, VA · In queue since December 2018 · Proposed COD September 2027

120 MW

Capacity

1

Components

Battery

7y 3m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 9m

Construction75%
Queue EntryDec 12, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-09-27

Project Details

State

VA

County

Loudoun

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

New Road 230 kV

Data Source

LBNL + Live