New Road Storage
120 MW storage in Loudoun, VA · In queue since December 2018 · Proposed COD September 2027
120 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-09-27
State
VA
County
Loudoun
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
New Road 230 kV
Data Source
LBNL + Live
Virginia gas plant moves ahead despite community objections | Energy
Tense public hearings and protests mocking Dominion Energy have followed the proposed natural gas plant in Chesterfield County, VA,...
Virginia gas plant moves ahead despite community objections | Energy
Tense public hearings and protests mocking Dominion Energy have followed the proposed natural gas plant in Chesterfield County, VA,...
Virginia gas plant moves ahead despite community objections | Energy
Tense public hearings and protests mocking Dominion Energy have followed the proposed natural gas plant in Chesterfield County, VA,...
Virginia gas plant moves ahead despite community objections | Energy
Tense public hearings and protests mocking Dominion Energy have followed the proposed natural gas plant in Chesterfield County, VA,...
Last updated 2026-03-26