Welcome Solar II
BetaActiveSolarBatteryPJMLBNL + Live
19.9 MW hybrid in Crawford, PA · In queue since September 2018 · Proposed COD August 2026
19.9 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 11m
Construction75%
Queue EntrySep 29, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-08-29
Project Details
State
PA
County
Crawford
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Andover (Maysville) 69kV I
Data Source
LBNL + Live