Welcome Solar II — Project Summary

Queue ID
PJM-AE1-237
Capacity
19.9 MW
Technology
Solar+Battery
Status
active
Location
Crawford, PA
Region
PJM
Developer
IA Status
IA Executed

Welcome Solar II

BetaActiveSolarBatteryPJMLBNL + Live

19.9 MW hybrid in Crawford, PA · In queue since September 2018 · Proposed COD August 2026

19.9 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 11m

Construction75%
Queue EntrySep 29, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-08-29

Project Details

State

PA

County

Crawford

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Andover (Maysville) 69kV I

Data Source

LBNL + Live

No news available for this project.