Pilesgrove Solar Project
149.3 MW generation in Salem, NJ · In queue since September 2018 · Proposed COD December 2027
149.3 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2027-12-31
State
NJ
County
Salem
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
Deepwater-Upper Pittsgrove 138 kV
Data Source
LBNL + Live
Large Dirt Hill In National Park NJ? Solar Farm
A large dirt hill has been forming in National Park NJ, along Grove Ave and Woodbury Creek. The Borough provides details on the project.
Philly's Clean Energy Goals Languish as Solar Farm Remains Unbuilt
An NBC10 investigation found that the City of Philadelphia's 70-megawatt solar farm, first announced in 2019, remains unbuilt. The project...
Large solar power facility approved for southern Millville; work likely starts in 2023
South of the Millville airport, solar energy developers are buying land from a mining company to build a 60-megawatt generating facility.
Large solar power facility approved for southern Millville; work likely starts in 2023
South of the Millville airport, solar energy developers are buying land from a mining company to build a 60-megawatt generating facility.
Last updated 2026-03-26