Raleigh Solar Project
BetaSuspendedSolarPJMLBNL + Live
90 MW generation in Raleigh, WV · In queue since September 2018 · Proposed COD June 2025
90 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 9m
Suspended75%
Queue EntrySep 10, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-06-25
Project Details
State
WV
County
Raleigh
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Grandview-Clifftop 138 kV
Data Source
LBNL + Live