Meadow Forge Solar Energy Center
BetaSuspendedSolarPJMLBNL + Live
130 MW generation in Delaware, IN · In queue since September 2018 · Proposed COD November 2026
130 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 2m
Suspended75%
Queue EntrySep 27, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-11-30
Project Details
State
IN
County
Delaware
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Delaware-Van Buren 138 kV
Data Source
LBNL + Live