Golden Aster Solar Energy Center
BetaSuspendedSolarPJMLBNL + Live
160 MW generation in Grant, IN · In queue since September 2018 · Proposed COD May 2026
160 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 8m
Suspended75%
Queue EntrySep 27, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-31
Project Details
State
IN
County
Grant
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Mississinewa-Gaston 138 kV
Data Source
LBNL + Live
No news available for this project.