Golden Aster Solar Energy Center — Project Summary

Queue ID
PJM-AE1-207
Capacity
160 MW
Technology
Solar
Status
suspended
Location
Grant, IN
Region
PJM
Developer
IA Status
IA Executed

Golden Aster Solar Energy Center

BetaSuspendedSolarPJMLBNL + Live

160 MW generation in Grant, IN · In queue since September 2018 · Proposed COD May 2026

160 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 8m

Suspended75%
Queue EntrySep 27, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-05-31

Project Details

State

IN

County

Grant

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Mississinewa-Gaston 138 kV

Data Source

LBNL + Live

No news available for this project.