800 MW generation in Sussex, VA · In queue since September 2018 · Proposed COD October 2029
800 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
11y 1m
Facilities Study50%
Queue EntrySep 25, 2018
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-01
Project Details
State
VA
County
Sussex
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Carson-Suffolk 500 kV
Data Source
LBNL + Live
No news available for this project.