Panther Grove Wind — Project Summary

Queue ID
PJM-AE1-163
Capacity
350 MW
Technology
Wind
Status
active
Location
Woodford, IL
Region
PJM
Developer
IA Status
IA Executed

Panther Grove Wind

BetaActiveWindPJMLBNL + Live

350 MW generation in Woodford, IL · In queue since September 2018 · Proposed COD February 2027

350 MW

Capacity

1

Components

Wind

7y 6m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 5m

Construction75%
Queue EntrySep 24, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-02-01

Project Details

State

IL

County

Woodford

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Powerton-Nevada 345 kV

Data Source

LBNL + Live