Maroon Solar
BetaSuspendedSolarPJMLBNL + Live
149 MW generation in Culpeper, VA · In queue since September 2018 · Proposed COD May 2027
149 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 8m
Suspended75%
Queue EntrySep 25, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-30
Project Details
State
VA
County
Culpeper
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Remington-Gordonsville 230 kV
Data Source
LBNL + Live