Bakers Pond Solar
100 MW generation in Prince George, VA · In queue since September 2018 · Proposed COD July 2026
100 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Proposed COD: 2026-07-01
State
VA
County
Prince George
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Disputanta-Poe 115 kV
Data Source
LBNL + Live
Prince George residents voice opposition to proposed solar farm
RWE Clean Energy is proposing new energy infrastructure near Pumphouse Road and Thweatt Drive. The project, called Bakers Pond Solar Farm,...
Prince George residents voice opposition to proposed solar farm
RWE Clean Energy is proposing new energy infrastructure near Pumphouse Road and Thweatt Drive. The project, called Bakers Pond Solar Farm,...
Last updated 2026-03-26