Northern Bobwhite Solar — Project Summary

Queue ID
PJM-AE1-143
Capacity
96 MW
Technology
Solar
Status
active
Location
Marion, KY
Region
PJM
Developer
IA Status
IA Executed

Northern Bobwhite Solar

BetaActiveSolarPJMLBNL + Live

96 MW generation in Marion, KY · In queue since September 2018 · Proposed COD March 2027

96 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 6m

Construction75%
Queue EntrySep 25, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-03-15

Project Details

State

KY

County

Marion

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Marion County 161 kV

Data Source

LBNL + Live

No news available for this project.