— Project Summary

Queue ID
PJM-AE1-114
Capacity
150 MW
Technology
Wind
Status
active
Location
Ogle, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveWindPJMLBNL

150 MW generation in Ogle, IL · In queue since September 2018 · Proposed COD December 2021

150 MW

Capacity

1

Components

Wind

7y 6m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 3m

Schedule

52 months past proposed COD

Impact Study25%
Queue EntrySep 13, 2018

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-31

Project Details

State

IL

County

Ogle

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Maryland-Lancaster 138 kV

Data Source

LBNL

No news available for this project.