Panther Grove 2
BetaActiveWindPJMLBNL + Live
300 MW generation in Woodford, IL · In queue since September 2018 · Proposed COD January 2028
300 MW
Capacity
1
Components
Wind
7y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 4m
Construction75%
Queue EntrySep 14, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2028-01-18
Project Details
State
IL
County
Woodford
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Mole Creek 345 kV
Data Source
LBNL + Live