Riverstone Solar — Project Summary

Queue ID
PJM-AE1-108
Capacity
149.5 MW
Technology
Solar
Status
active
Location
Buckingham, VA
Region
PJM
Developer
IA Status
IA Executed

Riverstone Solar

BetaActiveSolarPJMLBNL + Live

149.5 MW generation in Buckingham, VA · In queue since September 2018 · Proposed COD November 2027

149.5 MW

Capacity

1

Components

Solar

7y 6m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

9y 2m

Construction75%
Queue EntrySep 13, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-11-30

Project Details

State

VA

County

Buckingham

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Bremo-Scottsville 138 kV

Data Source

LBNL + Live