Riverstone Solar
149.5 MW generation in Buckingham, VA · In queue since September 2018 · Proposed COD November 2027
149.5 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
9y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-11-30
State
VA
County
Buckingham
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Bremo-Scottsville 138 kV
Data Source
LBNL + Live
Riverstone Solar faces potential penalties
Riverstone Solar's parent company, Apex Clean Energy, is accused of completely ignoring some of the conditions agreed upon.
Riverstone Solar faces potential penalties
Riverstone Solar's parent company, Apex Clean Energy, is accused of completely ignoring some of the conditions agreed upon.
Riverstone Solar faces potential penalties
Riverstone Solar's parent company, Apex Clean Energy, is accused of completely ignoring some of the conditions agreed upon.
Riverstone Solar faces accusations. Buckingham hires inspectors
The Riverstone Solar project is too big for Buckingham County staff to inspect. There's just too much space for one person to cover ...
Last updated 2026-03-26