Maidsville CCGT — Project Summary

Queue ID
PJM-AE1-105
Capacity
1270 MW
Technology
Gas
Status
active
Location
Preston, WV
Region
PJM
Developer
IA Status
IA Executed

Maidsville CCGT

BetaActiveGasPJMLBNL + Live

1,270 MW generation in Preston, WV · In queue since September 2018 · Proposed COD May 2029

1,270 MW

Capacity

1

Components

Gas

7y 6m

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

10y 8m

Construction75%
Queue EntrySep 6, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2029-05-30

Project Details

State

WV

County

Preston

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

North Longview 500 kV

Data Source

LBNL + Live

No news available for this project.