Maidsville CCGT
BetaActiveGasPJMLBNL + Live
1,270 MW generation in Preston, WV · In queue since September 2018 · Proposed COD May 2029
1,270 MW
Capacity
1
Components
Gas
7y 6m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10y 8m
Construction75%
Queue EntrySep 6, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2029-05-30
Project Details
State
WV
County
Preston
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
North Longview 500 kV
Data Source
LBNL + Live
No news available for this project.