BetaActiveSolarPJMLBNL
206.6 MW generation in Union, OH · In queue since August 2018 · Proposed COD December 2021
206.6 MW
Capacity
1
Components
Solar
7y 7m
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
3y 4m
Schedule
52 months past proposed COD
Impact Study25%
Queue EntryAug 31, 2018
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
OH
County
Union
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Blue Jacket-Kirby 138 kV
Data Source
LBNL