Strawhat Solar Energy Center
BetaSuspendedSolarPJMLBNL + Live
110 MW generation in Hardin, OH · In queue since August 2018 · Proposed COD January 2026
110 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 5m
Suspended75%
Queue EntryAug 31, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-01-14
Project Details
State
OH
County
Hardin
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
West Newton-Lynn 138 kV
Data Source
LBNL + Live